Strike Energy – Walyering being developed after 9 months

August 25, 2022
Strike Energy – Walyering being developed after 9 months
Life Of Mine
Strike Energy – Walyering being developed after 9 months

Aug 25 2022 |

/

Show Notes

Strike Energy (ASX:STX)

– The Walyering gas field has been sanctioned for development in only 9 months from its announced discovery. (55% Strike, 45% Talon Energy)
– Walyering will now transition into construction with a gross $14.4 million budgeted development cost. 
–  Commissioning gas is expected to enter the upstream facility by the end of CY22 with first gas sales targeted in Q1/23.  
– Strike has secured $10 million from Macquarie Bank Limited to fund its $7.9 million share of the development costs.

Other Episodes

Episode

January 18, 2023
Episode Cover

ASX Vanadium (RVT vs AVL), Leo Lithium adding to resource and Copper flying high – Channel Mine News 18 Jan

*** What do you know about Vanadium? *** Welcome to Channel Mine News, the go-to “in your ears” Mining news source for all the...

Listen

Episode

October 06, 2022
Episode Cover

Capricorn Metals (CMM) maiden profit of $89.5mil

Capricorn Metals (CMM) posted a maiden full year profit of $89.5mil. Sensational result, especially considering they run a 0.89g/t head grade and still achieve...

Listen

Episode

November 23, 2021
Episode Cover

NEW TO MINING & FIFO? – What you don‘t hear in Inductions

Don’t miss out on the Life Of Mine merch sale, 30% off storewide for XMAS. Head to https://lifeofminepodcast.com/shop/ and load up while its bloody...

Listen