Strike Energy (ASX:STX)
– The Walyering gas field has been sanctioned for development in only 9 months from its announced discovery. (55% Strike, 45% Talon Energy)
– Walyering will now transition into construction with a gross $14.4 million budgeted development cost.
– Commissioning gas is expected to enter the upstream facility by the end of CY22 with first gas sales targeted in Q1/23.
– Strike has secured $10 million from Macquarie Bank Limited to fund its $7.9 million share of the development costs.
*** What do you know about Vanadium? *** Welcome to Channel Mine News, the go-to “in your ears” Mining news source for all the...
Capricorn Metals (CMM) posted a maiden full year profit of $89.5mil. Sensational result, especially considering they run a 0.89g/t head grade and still achieve...
Don’t miss out on the Life Of Mine merch sale, 30% off storewide for XMAS. Head to https://lifeofminepodcast.com/shop/ and load up while its bloody...